CAP1910 Water Main ImprovementsContractor: FDM Contracting Inc. On S. Blair Street, the contractor will finish preparing the roadway for new pavement the week of October 14th. The contractor plans to begin paving the roadway towards the end of the week. Residents will receive a door hanger in advance so they can move their vehicles off the street.
BLAIR ST - TRASH & RECYCLING PICKUP: Trucks will not be able to access the street on OCTOBER 23RD. If desired, residents can place containers at the nearest street corner for pick up and retrieve containers at the end of the day. Please be sure to mark containers with your address.
On E. Harrison Ave, the contractor will begin water main connections on the east side of the railroad. Property owners who will be affected by shut offs will receive a door hanger notice the day beforehand with details.
Minor pavement restoration work will occur on Normandy west of Coolidge, Rockingham and Albert.
|