CAP1910 Water Main ImprovementsContractor: FDM Contracting Inc. The week of June 24th, the contractor plans to continue water main installation on Normandy Road west of Coolidge Hwy.
On Rockingham the contractor plans to finish pavement restoration and cleanup.
On Albert Ave, the contractor tentatively plans to connect the new water main at Harvard. Residents will be notified the day beforehand via door hanger if they will be affected by any required water shut-offs.
On Judson Ave, the contractor tentatively plans to work on pavement restoration, towards the end of the week, weather permitting.
No work is scheduled for the other project streets the week of June 24th.
|