CAP1806 S. Campbell Road Resurfacing
10 Mile Road to 11 Mile Road
Contractor: Iafrate Construction Company
The east half of S. Campbell Road remains closed for the first phase of construction, and traffic is currently shifted to the west side of the road. One lane is open in each direction. The following left turns are not allowed during this phase of construction:
- Northbound and southbound Campbell Road at 11 Mile Road
- Westbound Lincoln Avenue at S. Campbell Road
The contractor will begin closing driveways on the east side of the road between Sixth Street and Fourth Street starting on Friday August 3rd and residents will receive a door hanger beforehand with this information. Curb and gutter, concrete base and driveways are scheduled to be installed between Lincoln Avenue and E. Fourth Street throughout the week of August 6th.
Over the weekend, unsuitable material was discovered and additional excavation of the roadway is required.
At 7AM Monday August 3rd, the contractor will shut down the northbound lane of S Campbell Rd between Fourth Street and Third Street to proceed with the work.
Flaggers will maintain travel for both directions for the current southbound open lane.
You can find more information on the project at romi.gov/campbellroad