CAP1835 Road Reconstruction Improvements
Contractor: Hard Rock Concrete, Inc.
Informational Presentation: The Engineering Division prepared a presentation to discuss the details of this project. If you haven’t seen it, you can
view the presentation here.
Woodland Avenue - Webster Road to Glenwood Road
This street is substantially complete and the remaining handicap ramp is scheduled to be poured during the week of July 16th. The contractor will joint seal the new pavement in the coming weeks and will place “No Parking” signs along the road to allow for this work. Restoration is scheduled for this fall.
Bonnie View Drive - Lloyd Avenue to Northwood Boulevard
Work on this street is complete except for restoration.
Yorba Linda Boulevard - Fairlawn Avenue to Springer Avenue
The contractor plans to place concrete for the handicap ramp and one section of pavement at Fairmont Avenue during the week of July 16th. Plantings for the rain garden will not be installed until after Labor Day.
Parkway Drive - Normandy Road to Woodward Avenue
Work on this street is complete except for restoration.
Linwood Avenue - Webster Road to Glenwood Road
This road is now open to traffic. During the week of July 16th the contractor plans to install the remaining half of the intersection at Glenwood, some sidewalk and also a section of concrete that was improperly installed by the school. The contractor will joint seal the new pavement in the coming weeks and will place “No Parking” signs along the road to allow for this work. Restoration is scheduled for this fall.
Delaware Avenue - E. Kenilworth Avenue to E. Harrison Avenue
No work yet; the contractor tentatively plans to begin the work in July.