CAP1835 Road Reconstruction Improvements
Contractor: Hard Rock Concrete, Inc.
Informational Presentation: The Engineering Division prepared a presentation to discuss the details of this project. If you haven’t seen it, you can
view the presentation here.
Woodland Avenue - Webster Road to Glenwood Road
The contractor plans to replace some curbing at Webster Road handicap ramps, and the sidewalk for the ramps is scheduled to be installed during the week of July 9th.
Bonnie View Drive - Lloyd Avenue to Northwood Boulevard
Work on this street is complete except for restoration.
Yorba Linda Boulevard - Fairlawn Avenue to Springer Avenue
The contractor plans to replace concrete at the southeast corner of Fairmont Avenue and remaining sidewalk flags on Friday July 6th. Plantings for the rain garden will not be installed until after Labor Day.
Parkway Drive - Normandy Road to Woodward Avenue
Work on this street is complete except for restoration.
Linwood Avenue - Webster Road to Glenwood Road
The contractor plans to place concrete for the intersections at Webster Road and Glenwood Road on Friday July 7th. Linwood will likely remain closed until Wednesday July 11th while the concrete cures. Driveway approaches are tentatively planned for the same week. Please do not move barricades or drive on new concrete until the barricades are removed by the contractor.
Garbage and recycling: Garbage trucks will not be able to access the street on Monday July 9th. If desired, residents may drop off garbage and recycling receptacles at the corners of Webster or Glenwood before 7:00 a.m. and pick them up later in the day. The city recommends that residents have their address markings on all trash and recycling containers.
Delaware Avenue - E. Kenilworth Avenue to E. Harrison Avenue
No work yet; the contractor tentatively plans to begin the work in July.