CAP1835 Road Reconstruction Improvements
Contractor: Hard Rock Concrete, Inc.
Informational Presentation: The Engineering Division prepared a presentation to discuss the details of this project. If you haven’t seen it, you can
view the presentation here.
Woodland Avenue - Webster Road to Glenwood Road
The intersection of Glenwood and Woodland is planned to be open by the end of the day June 22nd. The contractor plans to back-fill and level the greenbelt areas during the week of June 25th and to place the handicap ramps at the intersection of Glenwood. The contractor is also required to replace the handicap ramps at Webster and the adjacent road panels. Placement of sod will not occur until after Labor Day in order to ensure growth.
Bonnie View Drive - Lloyd Avenue to Northwood Boulevard
Work on this street is complete.
Yorba Linda Boulevard - Fairlawn Avenue to Springer Avenue
The contractor has paved the north/east half of the road, and this section will remain closed until late next week while the concrete cures. The contractor plans to install the remaining driveway approaches on the south/west edge of the road during the week of June 25th, and also the remaining concrete area at the cul-de-sac.
Parkway Drive - Normandy Road to Woodward Avenue
The contractor plans to replace the remaining concrete patches on the south side of Parkway Drive and the handicap ramps at Arlington during the week of June 25th.
Linwood Avenue - Webster Road to Glenwood Road
The contractor plans to finish pavement removals on the west side of Linwood Avenue and will begin removals on the east half during the week of June 25th. Residents will receive a door hanger a day in advance when their driveway will no longer be available. Residents will likely be out of their driveways for 2 to 3 weeks while the contractor prepares and paves the road.
Delaware Avenue - E. Kenilworth Avenue to E. Harrison Avenue
No work yet; the contractor tentatively plans to begin the work in July.