CAP1835 Road Reconstruction Improvements
Contractor: Hard Rock Concrete, Inc.
Woodland Avenue - Webster Road to Glenwood Road
The contractor has completed installation of the water main on Woodland Avenue. The contractor will be performing pressure testing and bacteria testing of the water main the week of April 30th to ensure the water main is safe for public use. After all testing is approved, the contractor will connect the new water main pipe to the city’s water system. The connections typically require the water to be turned off for about four to eight hours, and residents will be notified of any water shutoffs 24 hours in advance with a door hanger.
Bonnie View Drive - Lloyd Avenue to Northwood Boulevard
The contractor has paved the west side of Bonnie View which is currently closed to traffic, and has begun removing the pavement on the east side of the road. The contractor tentatively plans to place concrete on the east half of the road during the week of April 30th, likely towards the end of the week.
Yorba Linda Boulevard - Fairlawn Avenue to Springer Avenue
The contractor is scheduled to begin pavement removals starting on April 27th. The contractor will remove half of the roadway pavement to allow for water main installation. One lane of pavement will be left in place for local traffic while the water main is constructed.
Parkway Drive - Normandy Road to Woodward Avenue
The contractor has poured the south/east side of the roadway and this pavement will be closed to vehicles through the week of April 30th. The contractor will begin pavement removals on the other half of the roadway later in the week.
Linwood Avenue - Webster Road to Glenwood Road
No work to begin until school is out for the summer.
Delaware Avenue - E. Kenilworth Avenue to E. Harrison Avenue
No work yet; the contractor tentatively plans to begin the work in late June or July.