CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor plans to replace the remaining halves of concrete road base in areas where utility work was performed towards the end of the week of September 18th. Short sections of the road may be closed to allow for this work but access from the cross streets will be available for residents. Once the remaining concrete road base is placed and cured, the contractor will install the hot mix asphalt for the roadway, likely during the week of September 25th.
Dallas Avenue
The newly paved section between Lenox and Stephenson will remain closed for most of the week while the concrete cures. The contractor plans to pour the remaining concrete returns at Lenox and Stephenson at the end of the week.
Lockwood Avenue
The contractor plans to install storm sewer and prepare the road for paving during the week of September 18th. The roadway is tentatively scheduled to be paved the following week.