CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor plans to finish all water main connections during the week of July 31st and plans to complete storm sewer and sanitary sewer improvements by the end of the week. The contractor will remove curbing and driveways along the roadway. Driveway approaches will be filled in with stone for resident access.
Dallas Avenue
The contractor plans to begin water main installation on Monday July 31st between Helene Avenue and Stephenson Highway. The new water main will be installed primarily in the north greenbelt of Dallas Avenue.
Fairview Avenue
The contractor has placed the road base material along Fairview Avenue. The road will be formed and paved after Kalama Avenue and Brinkey Avenue are paved and cured; at least two weeks from now.
Kalama Avenue and Brinkey Avenue
The contractor has prepared the road base material, and plans to begin forming for paving operations during the week of July 31st. Concrete placement for the roadway is tentatively scheduled for the end of the week or early following week. The pavement will remain closed for one week after concrete is placed to allow for curing. All paving work on these streets is scheduled to be completed by mid-August before school activities begin for the year.
Lockwood Avenue
Pavement removals are scheduled to begin the week of July 31st toward the end of the week. Pavement will only be removed to allow for water main installation at this time, primarily on the west side of the roadway. Driveway approaches that are removed will be filled in with stone to allow for resident access. Water main installation is tentatively scheduled for the second or third week in August.