CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor will continue water main connections and water service transfers to the new water main during the week of July 17th. Properties that will be without water during connections will be notified via door hanger the day beforehand. Shutdowns are typically 4 to 8 hours long.
The Department of Public Service will also be transferring water services on E. Hudson, west of Batavia Avenue.
Dallas Avenue
The contractor plans to begin driveway and sidewalk removals on Dallas Avenue the week of July 17th to allow for new water main installation. The removals are primarily on the north side of Dallas Avenue between Helene Avenue and Stephenson Highway.
Fairview Avenue
The contractor will finish road preparation work once Consumers Energy replaces an existing shallow gas main. This is expected to take place during the week of July 17th.
Kalama Avenue and Brinkey Avenue
The contractor plans to continue underground utility installations on Kalama Avenue between Brinkey Avenue and Stephenson Highway during the week of July 17th. Consumers Energy is also working to replace the gas main along Kalama Avenue.
Residents will receive door-hanger notices 24 hours in advance when driveways will be unavailable.