CAP1630 Special Assessment Paving Improvements
Contractor: Mark Anthony Contracting, Inc.
Bassett Road
Basset Road has been paved, and is open to local traffic only. The contractor plans to pour the drive approaches, sidewalk and ramps Friday May 26th (weather permitting), or early the following week if necessary. Sod restoration is expected to be performed in the next couple weeks.
Girard Road
Girard Road has been paved and is currently closed to traffic while the road cures. The road is scheduled to be open to local traffic only late next week, but access from Rochester Road will be closed. The contractor plans to pour the parking lanes on each side of Girard Road, just east of Rochester Road, the week of May 30th.
S. Edison Avenue
The contractor plans to perform the final water main connection on S. Edison Avenue on Saturday May 27th. Properties that will be without water during water main connections will be notified via door hanger the day beforehand. This shutdown will last approximately 8 hours. Grading and paving preparation work will begin after Memorial Day.Wrenford Road
Sod restoration is expected during the week of May 30th.Massoit Road
Sod restoration is expected during the week of May 30th.W. Park Avenue
The contractor tentatively plans to connect individual water services to the new water main during the week of May 30th. The final water main connection is also scheduled for next week. Properties that will be without water during water main connections will be notified via door hanger the day beforehand. Shutdowns are typically 4 to 8 hours long.