CAP1735 Road Reconstruction Improvements
Contractor: Mark Anthony Contracting, Inc.
Batavia Avenue
The contractor has started water main installation, which will continue throughout the week of May 22nd.
Several water services on Batavia have galvanized piping, which is typically fragile and prone to breaks. If a water service breaks during construction, the city will perform an emergency shutdown. Emergency shutdowns for service repairs typically last about 2 hours. As the contractor comes across galvanized water services, the city will notify individual residents.
Fairview Avenue
The contractor is planning to begin work on Fairview Avenue after Memorial Day.
The remaining streets are scheduled to be reconstructed in the following order:
- Dallas Avenue: Helene Avenue to Stephenson Highway
- Kalama Avenue: Brinkey Avenue to Stephenson Highway
- Brinkey Avenue: Kalama Avenue to Harwood Avenue
- Lockwood Avenue: Catalpa Drive to Crane Avenue