CAP1710 Water Main Improvements
Bellaire Avenue, Ferris Avenue, N. Vermont Avenue, Rochester Road
On Bellaire Avenue, the contractor will connect the new water main and perform service connections the week of April 10th.
On N. Vermont, the water main pipe has been installed and the contractor will perform pressure and bacteria testing on the water main next week prior to connection.
Properties that will be without water during water main connections will be notified via door hanger the day beforehand. Shutdowns are typically 4 to 8 hours long.
On Ferris Avenue, all water main work is now complete. The contractor has back-filled the excavated areas, and will replace concrete at a future date (likely in several weeks). The road is fully open to traffic.