CAP2410 Water Main Improvements
All water main installation and connections are complete for both streets, only roadwork is remaining.
On Northwood, the contractor has installed the new speed humps on the westbound lanes last week. Once the concrete cures they will switch to the eastbound side of the road, tentatively scheduled for Thursday pending inclement weather.
The contractor will also continue working on cleanup and landscape restoration this week on both Northwood and Sycamore.