CAP2410 Water Main Improvements
All water main installation and connections are complete for both streets, only roadwork is remaining.
On Northwood & Sycamore, the contractor has begun paving the first layer of asphalt on the roadways. Once complete they will be adjusting sewer structures for the final roadway height the reminder of the week.
The contractor will also be working on cleanup and backfilling in advance of Halloween.