CAP2415/2416 Asphalt Resurfacing
This project will resurface several streets in the residential neighborhoods and the downtown.
CAP2416 Downtown
Paving is now complete on the project streets downtown. This week the contractor plans to work on cleanup and finish striping the roadways.
CAP2415 Neighborhoods
Phase 2: The contractor is paving the first layer of asphalt today and tomorrow. Once complete crews will spend the rest of the week adjusting sewer structures for the final roadway height. Final paving is tentatively scheduled for early next week.
Some tree branches were damaged during milling operations, so the Forestry Division will be out to trim the trees once final paving is completed.
Phase 3: Construction is starting on Phase 3 streets this week beginning with W. Hudson and working south. Crews will start with concrete work first, working on one side of the roadway at a time.