CAP2435 Road Reconstruction
This project will completely reconstruct several roads in the city. The table below shows the streets that will be reconstructed this year and the full project map linked above shows the project streets in green. New water main will also be installed on Parkview and Vinsetta. This project is scheduled to start the week of April 8th.
On Albert Avenue, the contractor will continue to work on pavement removal this week. The concrete team is setting up forms and grading the areas that have been removed completely.
On Samoset, the contractor will start pouring Tuesday and plans to finish by Wednesday, weather permitting.
On Parkview, the water main testing will continue on Monday and Tuesday. Once that is complete the contractor will begin connecting the new main to the existing watermain system. Shut off notices will be passed out a day before any water connection or service work starts.
On Vinsetta, the open cut excavation and water main pipe installation will begin on Monday and finish on Tuesday, then water main testing will begin.
*As part of this project the contractor will also be installing traffic calming chicanes on Marais Avenue between Thistle and Lexington as approved by the city commission.