CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
Phase 1
All the project streets in Phase 1 are complete, with minor restoration work remaining.
Phase 2
For Delemere, the contractor completed paving over the weekend. New pavement markings and restoration is scheduled this week.
Phase 3
On University, Pingree and Fairgrove concrete work is complete. The contractor is scheduling the roadways to be milled (remove top layers of asphalt), likely after the holiday weekend.
On Alexander and Troy, the contractor plans to begin concrete work this week.
On Amelia, the city's contractor has started concrete work on the block between Rochester and Blair, where the gas company has finished their underground work. Work between Blair and Campbell will likely begin in two weeks once Consumer's Energy is finished.
On Connecticut, the gas company plans to finish their work before the July 4th holiday and the city will begin the roadwork after, tentatively scheduled t begin the week of the 11th.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.