CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
Phase 1
All the project streets in Phase 1 are complete, with minor restoration work remaining.
Phase 2
For Delemere, the contractor completed milling the roadway surface between Nakota and Normandy last week. Minor restoration and manhole adjustments will occur this week before the final layer of pavement is placed. The contractor plans to mill the roadway surface between Normandy and 14 Mile this week in preparation for final paving this weekend.
Phase 3
On University, Pingree and Fairgrove concrete work was completed this week. The contractor plans to mill the roadways towards the end of the week/beginning of next week.
On Alexander and Troy, the contractor plans to begin concrete work later this week.
On Amelia, the city's contractor has started concrete work on the block between Rochester and Blair, where the gas company has finished their underground work. Work between Blair and Campbell will likely begin in two weeks once Consumer's Energy is finished.
On Connecticut, the gas company plans to finish their work before the July 4th holiday and the city will begin the roadwork after.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.