CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
Phase 1
All the project streets in Phase 1 are complete, with restoration work finishing up.
Phase 2
On Vermont, the contractor has completed all paving work an the road is open. Landscaping restoration work continues this week.
For Delemere, the contractor plans to finish the majority of the concrete work this week. Then they plan to do most of the landscaping restoration prior to milling and paving the roadway.
Phase 3
Work on Phase 3 streets is scheduled to begin this week, starting on University. The contractor will work on one side of the street at a time, beginning with curbing first.
*Amelia and Connecticut work is expected to begin in a few weeks once Consumers Energy is completed with their gas work.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.