I-75 Freeway & 11 Mile Road Bridge Work


The 11 Mile Road bridge across I-75 freeway will be closed through November for reconstruction.

Questions or concerns regarding the bridge and freeway work should be sent to Oakland Corridor Partners who are overseeing Segment 3 of the construction for MDOT.


Call:    586.486.3626
Email:  info@ocp-i75.com

CAP2008 - Crooks Road Resurfacing

Contractor: Blaze Contracting, Inc.


Crooks Road work is now complete and the road is fully reopened to traffic. The contractor still has some cleanup and restoration work to do and will finish up in the coming weeks.

CAP2105 Concrete Street Repairs

Contractor: Mark Anthony Contracting, Inc.


Phase 4

The contractor will continue removing and replacing deteriorated road panels this week on one side of the street at a time.

map of Phase 4 streets
CAP2105 - Phase 4
slow down for work zones sign

CAP2110 Water Main Improvements

Contractor: FDM Contracting, Inc.


Vermont Avenue - Between Houstonia and Parkdale, the contractor is backfilling lawn areas that were dug up in preparation for final restoration. Between Parkdale and Girard, the contractor is prepping and pouring the east side with new concrete.
 
Parkdale Avenue - The contractor plans to finish lawn restoration in late September.
 
Houstonia Avenue - ROAD CLOSURE - Houstonia will be closed at N. Vermont while the contractor replaces pavement within the intersection. See photo below for closure location. Motorists will still be able to travel north/south through the intersection on N. Vermont Avenue. The contractor plans to finish lawn restoration in late September.
 
DeVillen Avenue - The contractor will be performing concrete restoration and patching some locations of the roadway between N. Blair and N. Vermont.

Girard Avenue - The contractor will begin concrete restoration work late September.

Glendale Avenue - The contractor has begun concrete restoration on the east side. Residents will be notified via doorhanger the day beforehand if they will lose driveway access.

14 Mile Road - Water main installation is complete. This week the new main will undergo testing.

Downtown Alleyways - East of Main Street, between Third St and Fifth St - Contractor is mobilizing equipment to the area in preparation to begin work.

aerial view of intersection showing Houstonia Avenue closed just east of Vermont Avenue
Road Closure at E. Houstonia and N. Vermont

Cloudy Water
Water can appear cloudy and/or rusty whenever there is a large draw of water from the water main, which is relatively common near water main projects. This can occur when water valves are opened and closed, when there are water main breaks, and when hydrants are flushed or used by the Fire Department.

Naturally occurring mineral deposits that accumulate within the water main get stirred up and become suspended particles, thus producing the discoloration in the water. Discolored water is temporary, and while unappealing, it is not harmful.

What to do?
Residents should run the cold water faucet closest to the meter (usually located in the basement or outside hose bib) for several minutes until the water runs clear. If the water does not clear after 20 minutes of flushing, contact the Engineering Division at 248.246.3260 or the Department of Public Service at 248.246.3300. Residents should avoid running hot water or washing clothes while water is discolored.

CAP2115 Asphalt Resurfacing Improvements

Contractor: Hutch Paving, Inc.


Tonawanda - The contractor plans to pave the roadway this week.

Lawn restoration will occur on the remaining streets during the next few weeks.

Phasing of streets

CAP2135 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


(Weather permitting) The contractor is working on landscape restoration on the project streets: Clean-up, backfilling, installation of top soil and seed/sod.

DeVillen Avenue - The contractor has closed DeVillen between N. Connecticut and Campbell tor reconstruct the entire roadway. The remaining concrete work has been poured, and the road will be re-opened at the end of the week once the concrete passes a strength test. Then lawn restoration will be done in the following weeks.

CAP2002 Sidewalk Improvement Program

Contractor: Italia Construction, Inc.


In the neighborhood south of 12 Mile Road and east of Main Street concrete crews are finishing the second halves of each street, and lawn restoration crews are working their way through the neighborhood.

The contractor plans to begin removals on first halves in the neighborhood north of 12 Mile this week as well, pouring later in the week or beginning of next week, weather dependent.

If you would like to meet with the inspector on site regarding your sidewalk, please call 248.246.3260 to schedule an appointment.

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2021 project map, find copies of mailed construction notices, and read about the city's various construction projects.