Improving Royal Oak
2021 project map
modernize 75 logo

I-75 Freeway & 11 Mile Road Bridge Work


The 11 Mile Road bridge across I-75 freeway will be closed through November for reconstruction.

Questions or concerns regarding the bridge and freeway work should be sent to Oakland Corridor Partners who are overseeing Segment 3 of the construction for MDOT.


Call:    586.486.3626
Email:  info@ocp-i75.com

CAP2008 - Crooks Road Resurfacing

Contractor: Blaze Contracting, Inc.


This week the contractor will be paving the first layer of asphalt and then adjusting drainage structures along the corridor for the final road height.

CAP2105 Concrete Street Repairs

Contractor: Mark Anthony Contracting, Inc.

CAP2105 Phase 2 Map
PHASE 2

The contractor will be continuing work on finishing the remaining patches in Phase 2 & Phase 3, and working on clean up and restoration in completed areas.

CAP2105 Phase 3 Map
PHASE 3
slow down for work zones sign

CAP2110 Water Main Improvements

Contractor: FDM Contracting, Inc.


Vermont Avenue - The new water main installed between Parkdale and Girard will continue to undergo testing this week. The contractor will be transferring services between 12 Mile and Parkdale to the new main, followed by grading in preparation for concrete restoration.
 
Parkdale Avenue - The contractor is working on restoration this week, replacing concrete that was damaged due to water main work.
 
Houstonia Avenue - The contractor is working on restoration this week, replacing concrete that was damaged due to water main work.
 
DeVillen Avenue - The contractor will be working on replacing the sidewalk that runs along Red Run Park with road work to follow.

Girard Avenue - The new water main will continue to undergo testing this week.

Glendale Avenue - The contractor will begin connecting the new main to the existing system this week. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.

11 Mile Road/Stephenson - Water main installation continues this week and connections to the existing system. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.

14 Mile Road - Traffic control equipment and materials have been delivered to site.  The contractor plans to begin new water main installation between Rochester and Campbell beginning in August.

Cloudy Water
Water can appear cloudy and/or rusty whenever there is a large draw of water from the water main, which is relatively common near water main projects. This can occur when water valves are opened and closed, when there are water main breaks, and when hydrants are flushed or used by the Fire Department.

Naturally occurring mineral deposits that accumulate within the water main get stirred up and become suspended particles, thus producing the discoloration in the water. Discolored water is temporary, and while unappealing, it is not harmful.

What to do?
Residents should run the cold water faucet closest to the meter (usually located in the basement or outside hose bib) for several minutes until the water runs clear. If the water does not clear after 20 minutes of flushing, contact the Engineering Division at 248.246.3260 or the Department of Public Service at 248.246.3300. Residents should avoid running hot water or washing clothes while water is discolored.

CAP2115 Asphalt Resurfacing Improvements

Contractor: Hutch Paving, Inc.


Phase I

Star - The contractor has tentatively planned to mill the existing roadway this week.

Phase II

Highfield - The contractor plans to pave the final layer of asphalt this week.

Landscape restoration continues on the project streets.


Phase III

Hampton -  The contractor will continue paving work this week, weather permitting.

Tonawanda - waiting for new water/sewer services to be installed for the new houses near 14 Mile Road. Once complete the contractor will begin curbing removals on the east side of the roadway first.

Chester - Sewer installation was completed last week. This week the contractor is prepping the road base and paving the first layer of asphalt. Curbing repairs continue.

Edgar -  (north of 13 Mile Rd. to Starr) Paving work will continue this week on Edgar and Starr, weather permitting.

Phasing of streets

CAP2135 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


(Weather permitting) The contractor is working on landscape restoration on the project streets: Clean-up, backfilling, installation of top soil and seed/sod.

Nakota Road & Samoset Road - The new road pavement has been placed and the contractor will continue work on replacing driveway approaches and sidewalk ramps this week.

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2021 project map, find copies of mailed construction notices, and read about the city's various construction projects.