CAP2008 - Crooks Road Resurfacing

Contractor: Blaze Contracting, Inc.


This week the contractor will be pouring concrete for the new roadway.

CAP2105 Concrete Street Repairs

Contractor: Mark Anthony Contracting, Inc.

CAP2105 Phase 2 Map
PHASE 2

The contractor will be working on clean up and restoration this week on Phase 2 streets.
 
The contractor will continue removing and pouring sections of concrete on Phase 3 streets this week.

CAP2105 Phase 3 Map
PHASE 3

CAP2110 Water Main Improvements

Contractor: FDM Contracting, Inc.


Vermont Avenue - Continuing water main installation between Parkdale and Girard. The contractor has tentatively scheduled to transfer the water services to the new main between 12 Mile and Parkdale Avenue next week. Residents individual water services will be shut off briefly (approx. 30 min.) for this work and they will be notified beforehand.
 
Parkdale Avenue - Connecting new water main to the existing system. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.
 
Houstonia Avenue - Connecting new water main to the existing system. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.
 
DeVillen Avenue - Connecting new water main to the existing system. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.

Glendale Avenue - The new water main is installed and will undergo testing this week.

14 Mile Road - The contractor plans to begin new water main installation between Rochester and Campbell beginning in August.

Cloudy Water
Water can appear cloudy and/or rusty whenever there is a large draw of water from the water main, which is relatively common near water main projects. This can occur when water valves are opened and closed, when there are water main breaks, and when hydrants are flushed or used by the Fire Department.

Naturally occurring mineral deposits that accumulate within the water main get stirred up and become suspended particles, thus producing the discoloration in the water. Discolored water is temporary, and while unappealing, it is not harmful.

What to do?
Residents should run the cold water faucet closest to the meter (usually located in the basement or outside hose bib) for several minutes until the water runs clear. If the water does not clear after 20 minutes of flushing, contact the Engineering Division at 248.246.3260 or the Department of Public Service at 248.246.3300. Residents should avoid running hot water or washing clothes while water is discolored.

CAP2115 Asphalt Resurfacing Improvements

Contractor: Hutch Paving, Inc.


Phase I

All asphalt milling and paving is complete except for a portion of Starr Road** on hold.

Landscape restoration crews will continue to work this week on grading, top soil, seeding and sprinkler repairs (weather permitting).

**Starr between 13 mile and Benjamin is currently on hold awaiting sewer repairs.

Phase II

The contractor has completed paving on most of the Phase II streets.

Highfield - Once Consumers Energy complete gas main improvements, crews will prep to mill and pave. Estimated gas work completion is one week.

Landscape restoration will begin as landscape crews complete work on Phase I streets, expected to start on Phase II streets this week.


Phase III

Hillside (cul-de-sac) - Final paving is scheduled for the week of July 5th.

Samoset, Grandview and Buckingham - Paving is scheduled for this week, weather permitting.

Hampton -  The contractor will be working on subgrade removal and stone placement and edge drain installation, followed by new curbing and driveway approaches.

Tonawanda curbing replacement is tentatively scheduled to begin next week.

Chester - A relief sewer will be installed on Chester east of Mandalay. This work is tentatively scheduled to begin next week. Once complete, crews will start prep work for paving.

Edgar -  north of 13 Mile Rd. to Starr starting in July after the holiday and Art in the Park event.

Phasing of streets

CAP2135 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


(Weather permitting) The contractor is working on landscape restoration on the project streets: Clean-up, backfilling, installation of top soil and seed/sod.

Nakota Road - The contractor has prepped the roadway and plans to begin pouring new roadway pavement this week, weather permitting.

Samoset Road - The contractor will be finishing prep work to begin pouring the new roadway this week, weather permitting.

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2021 project map, find copies of mailed construction notices, and read about the city's various construction projects.