CAP2115 Asphalt Resurfacing Improvements
Contractor: Hutch Paving, Inc.
Phase I
All asphalt milling and paving is complete except for a portion of Starr Road** on hold.
Landscape restoration crews will continue to work this week on grading, top soil, seeding and sprinkler repairs (weather permitting).
**Starr between 13 mile and Benjamin is currently on hold awaiting sewer repairs.
Phase II
The contractor has completed paving on most of the Phase II streets.
Highfield - Once Consumers Energy complete gas main improvements, crews will prep to mill and pave. Estimated gas work completion is one week.
Landscape restoration will begin as landscape crews complete work on Phase I streets, expected to start on Phase II streets this week.
Phase III
Hillside (cul-de-sac) - Final paving is scheduled for the week of July 5th.
Samoset, Grandview and Buckingham - Paving is scheduled for this week, weather permitting.
Hampton - The contractor will be working on subgrade removal and stone placement and edge drain installation, followed by new curbing and driveway approaches.
Tonawanda curbing replacement is tentatively scheduled to begin next week.
Chester - A relief sewer will be installed on Chester east of Mandalay. This work is tentatively scheduled to begin next week. Once complete, crews will start prep work for paving.
Edgar - north of 13 Mile Rd. to Starr starting in July after the holiday and Art in the Park event.