CAP2115 Asphalt Resurfacing Improvements
Contractor: Hutch Paving, Inc.
Phase I
All asphalt milling and paving is complete except for a portion of Starr Road** on hold. Landscape restoration crews will continue to work this week on grading, top soil, seeding and sprinkler repairs.
A relief sewer will be installed on Chester east of Mandalay in the next few weeks. Once complete, crews will start prep work for paving.
**Starr between 13 mile and Benjamin is currently on hold awaiting sewer repairs, tentatively scheduled for this week.
Phase II
All streets have received their base coarse of asphalt and top coarse should be completed this week.
Highfield - Once Consumers Energy complete gas main improvements, crews will prep to mill and pave. Estimated gas work completion is three weeks.
Landscape restoration will begin as landscape crews complete work on Phase I streets.
Phase III
Hillside (cul-de-sac) will be milled and then paved later this week.
Concrete work on Samoset and Grandview is complete, and Buckingham should be finished by week end.
Hampton is tentatively scheduled for pavement removal mid-week.
Tonawanda is on hold while DPS installs new water services for some new construction homes on the block. Expected to be completed this week.
Edgar north of 13 Mile Rd. to Starr starting in July after the holiday.