Improving Royal Oak
2021 project map

CAP2008 - Crooks Road Resurfacing

Contractor: Blaze Contracting, Inc.


Construction is progressing with the following items planned for this week: finishing up pavement removal and excavating the roadway in preparation for new aggregate base and roadway pavement. 

CAP2105 Concrete Street Repairs

Contractor: Mark Anthony Contracting, Inc.

CAP2105 Phase 2 Map
PHASE 2

Will be working on the remaining halves of road repairs in Phase 2, including pouring, backfilling, joint sealing and restoration.
 
Will continue removing first halves in Phase 3, which includes pouring, saw cutting, pavement removal and pouring of new concrete.


CAP2105 Phase 3 Map
PHASE 3

CAP2110 Water Main Improvements

Contractor: FDM Contracting, Inc.


Vermont Avenue - Continuing water main installation between Parkdale and Girard. The contractor also plans to transfer the water services to the new main between 12 Mile and Houstonia. Residents individual water services will be shut off briefly (approx. 30 min.) for this work and they will be notified beforehand.
 
Parkdale Avenue - Connecting new water main to the existing system. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.
 
Houstonia Avenue - Connecting new water main to the existing system. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.
 
DeVillen Avenue - Chlorinating and flushing new water main for bacteria testing. Once complete, connecting new water main to the existing system. This requires a water shut-off and any affected residents will be notified the day beforehand with the time and duration.

Glendale Avenue - Begin water main installation via directional drilling. Midland Avenue will be closed at the east side of Glendale for two weeks during water main installation.

CAP2115 Asphalt Resurfacing Improvements

Contractor: Hutch Paving, Inc.


Phase I

All asphalt milling and paving is complete except for a portion of Starr Road** on hold. Landscape restoration crews will continue to work this week on grading, top soil, seeding and sprinkler repairs.

A relief sewer will be installed on Chester east of Mandalay in the next few weeks. Once complete, crews will start prep work for paving.

**Starr between 13 mile and Benjamin is currently on hold awaiting sewer repairs, tentatively scheduled for this week.

Phase II

All streets have received their base coarse of asphalt and top coarse should be completed this week.

Highfield - Once Consumers Energy complete gas main improvements, crews will prep to mill and pave. Estimated gas work completion is three weeks.

Landscape restoration will begin as landscape crews complete work on Phase I streets.


Phase III

Hillside (cul-de-sac) will be milled and then paved later this week.

Concrete work on Samoset and Grandview is complete, and Buckingham should be finished by week end.

Hampton is tentatively scheduled for pavement removal mid-week.

Tonawanda is on hold while DPS installs new water services for some new construction homes on the block. Expected to be completed this week.

Edgar north of 13 Mile Rd. to Starr starting in July after the holiday.

Phasing of streets

CAP2135 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


The contractor is working on landscape restoration on the project streets: Clean-up, backfilling, installation of top soil and seed/sod.

Massoit Road
- Some minor concrete work remains and landscape restoration.

Greenfield Alley - The contractor plans to pour concrete driveways and sidewalks this week.

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2021 project map, find copies of mailed construction notices, and read about the city's various construction projects.

Copyright 2020 Royal Oak. All Rights Reserved.
203 S Troy Street, Royal Oak, Michigan 48067

Powered by
CivicSend - A product of CivicPlus