|
CAP2008 - Crooks Road ResurfacingContractor: Blaze Contracting, Inc.Construction is progressing with the following items planned for this week:
|
|
|
|
|
CAP2101 DPS Patches & Pre-Paid Sidewalk RepairsContractor: Italia Construction, Inc. Italia is continuing to saw cut and remove the roadway and sidewalk panels. Replacement of the hard surfaces shall follow shortly after removals. Landscape restoration is planned with topsoil, seed and mulch the third week of June.
|
|
|
|
CAP2105 Concrete Street RepairsContractor: Mark Anthony Contracting, Inc.
|
|
|
|
 PHASE 2
|
|
|
Will be working on the remaining halves of road repairs in Phase 2, including pouring, clean-up, joint sealing and restoration. Will continue removing first halves in Phase 3, which includes pouring, saw cutting and removals.
|
|
|
 PHASE 3
|
|
|
|
CAP2110 Water Main ImprovementsContractor: FDM Contracting, Inc.
Vermont Avenue - Chlorinating and flushing water main for bacteria testing; Week of June 21st- possible transferring residential water services between 12 Mile Road and E. Houstonia Avenue; Week of June 21st- continue to install water main between Parkdale Avenue and Girard Avenue. Parkdale Avenue - Chlorinating and flushing water main for bacteria testing. Houstonia Avenue - Chlorinating and flushing for water main for bacteria testing; Pressure test N. Wilson Avenue to Campbell Road water main; Week of June 21st- first water connection to the existing water system at the west side of N. Wilson Avenue. DeVillen Avenue - Installing water main at N. Vermont Avenue intersection; Chlorinating and flushing water main for bacteria testing; Pressure test water main.
|
|
|
|
CAP2115 Asphalt Resurfacing ImprovementsContractor: Hutch Paving, Inc.
Phase I
The milling of the existing asphalt pavement is complete except for Starr** portion on hold.
Final asphalt paving is complete.
Restoration Landscape crew was working on restoration last week and will continue this week moving into phase two streets with grading, topsoil, seed and mulch, and sprinkler repairs.
**Starr between 13 mile and Benjamin is currently on hold waiting for sewer repairs additional remaining west end concrete repairs will happen early this week.
Phase II
Quite a few of the streets were paved or received the base coarse of asphalt late last week: Greenway, Starr east of Woodward, and first block of Chester east of Woodward are paved. Hunter east of Woodward and Elmwood (was topped) will receive paving Monday afternoon. Edgar south of Normandy – top coarse was installed late in the week Hillside Ct. (loop) curbing and driveways are complete and will be looking to be milled mid-week to the end of the week.
Highfield - the removals of pavement and curbing is complete. We are waiting on Consumers Energy to complete gas main improvements prior to milling and paving. We are looking at Consumers schedule with their ETA to completion being around 3 weeks before we can wrap up.
Restorations occuring after Phase I is complete (see Phase I note).
Phase III
Possible start Tuesday/Wednesday of the week on Samoset, Grandview east of Woodward and Buckingham west of Woodward.
The remaining streets Tonawanda, Hampton are looking to be sometime during or after the week of the 20th
Edgar north of 13 Mile Rd. to Starr starting in July.
|
|
|
|
|
CAP2135 Road Reconstruction ImprovementsContractor: Mark Anthony Contracting, Inc.
Massoit Road - The contractor is wrapping up work by backfilling and restoring lanscaped areas and will be cleaning up a bit more.
Greenfield Alley - The contractor plans to pour concrete on Tuesday (weather permitting).
|
|
|
|
Consumers Energy Neighborhood Grid Projects
Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade
|
|
|
|
|
Below is a quick summary of work done this past week on the 2 grid projects, ROK1 & ROK2. The map below shows the location of those 2 projects, but not necessarily the phase (or area) of current work.
|
|
|
|
|
Both projects have been affected by reduced work crew sizes (due to Covid-19, training, and other absences) which has slowed productivity some. Although the absence rates are getting lower, Consumers continues to manage through these challenges in order to maintain their goal to complete the projects before year end. Restoration is also slowed due to employee attrition & Covid-19 absences.
ROK1: - This past week crews worked along Grandview, Sheridan, Arden, Greenfield, Berkshire, Mankato, and Seminole streets.
- Consumers is near completion of phase 6. The bulk of work is in the phase 1 area.
- Next week Consumers plans to continue work along Greenfield, Normandy and Berkshire streets.
- Adjustments to Consumers' traffic control plan along Greenfield have made some improvement. Police presence has aided significantly. As before, Consumers will continue to monitor this situation since employee safety and public safety is at risk.
ROK2:- This past week crews worked along Main, Orchard Grove, Greenleaf, Poplar, Evergreen, Maple and Maxwell streets.
- Consumers is completing restoration work on phase 1 and installations in phase 5 & 1.
- Next week crews will be on Main, Hickory, Evergreen, Maxwell, Maple, Woodsboro, Cedar Hill, Butternut and streets.
Work Schedule: - Consumers is now working 10 hour days Monday through Thursday, 8 hour days on Fridays and voluntary 8 hour days on Saturdays.
- The proposed construction schedules for each project are listed below so that you can coordinate with any city activity/work.
- Below are the planned start/finish dates for each grid project:
|
|
|
|
|
While working on weekends Consumers crews will be conscious of disruptions our presence may have and will be engaged in creative ways to minimize noise and other impacts to the residences.
|
|
|
|
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.
You can visit www.romi.gov/currentprojects to view the 2021 project map, find copies of mailed construction notices, and read about the city's various construction projects.
|
|
|
|
|
|