Improving Royal Oak
2021 project map

CAP2008 - Crooks Road Resurfacing


On Wednesday, May 12th, the contractor plans to modify the traffic control on Crooks Road from Stage 1A to Stage 1B to mill and resurface with asphalt the western half of Crooks Road.  In order to conduct these operations, the center turn lane between Lexington Boulevard to Normandy Road will be eliminated and left turns movements will not be allowed southbound on Lexington Boulevard and for Normandy Road for both northbound and southbound directions.

Motorists are advised to adjust their travel routes if they currently use these movements.  These operations are expected to last until May 24, where traffic will be shifted to the west side of Crooks and construction on the east half of Crooks will begin.

Traffic control plan for Crooks Road

CAP2105 Concrete Street Repairs

Contractor: Mark Anthony Contracting, Inc.

Phase 1 Streets
PHASE 1

This week the contractor will be prepping and pouring concrete on the west side of Phase 1 streets.

The contractor also plans to begin removals on the east side of Phase 2 streets this week, beginning with Mclean. 

Phase 2 Streets
PHASE 2

CAP2110 Water Main Improvements

Contractor: FDM Contracting, Inc.


Mobilization and installation of traffic control devices will begin on the below streets this week. Construction is tentatively scheduled to begin the week of May 17th.

  • N. Vermont Avenue
  • E. Houstonia Avenue
  • Parkdale Avenue
  • Girard Avenue.

CAP2115 Asphalt Resurfacing Improvements

Contractor: Hutch Paving, Inc.


Phase I
All the concrete work on Phase 1 streets is complete. The contractor will begin milling off the existing asphalt this week in the following order: Elmhurst, Rosewold, Nakota & Elmhurst at Starr.

The section of Starr between 13 Mile and Benjamin is on hold for a sewer repair.

Phase II
Concrete work is beginning on Phase 2 streets this week. The contractor will be working on the east side of the project streets first.

Phasing of streets

CAP2135 Road Reconstruction Improvements

Contractor: Mark Anthony Contracting, Inc.


Massoit Road - The contractor is working on pavement removal, grading and installing new edge drain this week.

Manor Avenue and Cresthill Avenue - The contractor plans to pour the new driveway approaches this week.

Chester Road - The contractor will be performing some minor grading this week.

street list

Consumers Energy Neighborhood Grid Projects


Consumers Energy is upgrading the gas pipeline infrastructure with some large neighborhood projects this summer, as shown in YELLOW on the project map above. To learn more visit: ConsumersEnergy.com/pipelineupgrade 

picture of worker digging
Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2021 project map, find copies of mailed construction notices, and read about the city's various construction projects.