CAP2010 Water Main Improvements
Contractor: FDM Contracting, Inc.
The city's contractor has been authorized to use the northeast section of VFW Park for construction staging and material storage. The area will be fenced off for public safety. Vehicles will enter/exit using Campbell Road and Sixth Street. Once the project is complete, the disturbed areas will be re-graded and restored with topsoil and seed. The contractor will also make some park improvements by planting new trees and installing new picnic tables.
Fifth Street - The week of August 24th, the contractor will be pouring concrete sidewalks and ramps and waiting on cure time.
S. Rembrandt Avenue - The contractor will be pouring new concrete roadway patches, sidewalks and ramps, and some sections of the adjacent alley.
Seventh Street - This week the contractor will be pouring new concrete driveway approaches, sidewalks and ramps and waiting on cure time.
S. Altadena Avenue - This week the contractor will continue replacing curbing, driveway approaches, sidewalks and ramps on the west side of the roadway.
S. Vermont Avenue - The contractor will finish transferring individual water services to the new main this week and addressing lead or galvanized services. Once complete they will begin the road work.
Helene Avenue - The contractor will continue replacing concrete sidewalks and ramps this week.
Longfellow Avenue - The contractor will begin transferring water services to the new main this week and addressing private water services that are lead or galvanized.
Farnum Avenue & 11 Mile Road - Work is tentatively scheduled to begin within two weeks.